Phase VIb - Finishing the Den, Part II / Floor, Laundry & Bar
With the shed finished just before winter, we will be taking a break from construction to work on other projects until spring. At that time we will start this last step of the den remodel. We will raise the floor to match the new stem wall and the rest of the house, add the partition to separate it from the master bedroom closet and add the laundry and bar. Meanwhile, we found some nice laminate flooring at the Habitat for Humanity outlet that we really liked for the den and purchased it to be stored until ready for it.
. . . Another (Shorter) Long Pause . . .
As often happens, plans and reality don't necessarily match. Instead of "next spring" it was spring but a couple of years later. I finally determined that if we were ever going to have the room finished, now was the time to get it done. Working on the floor does not agree with my arthritis a lot these days so I would need a lot of help from my carpenter son.
The first step was to raise the floor to match the rest of the house. Remember in a previous phase we built a false stem wall around the perimeter to match the main foundation then rebuilt the walls on it. This is not part of the den, of course, but I also wanted to cut a hole through the south wall of the living room to construct an alcove for the piano that does encroach into the new walk-in closet that is part of the den remodel. A concrete slab for the alcove had to be done before we could raise the rest of the floor so it is mentioned here. The slab was poured first then the rest of the alcove was built after installing the sub floor for the den. It is described more fully here.
All right, back to the den. The old slab floor was a porch so it had a slope to
the back of about 2 inches. We would cut 2x4s to set on the slab, tapered to make
their tops level and flush with the existing slab in the rest of the house. I
figured we could measure the depth at both ends then cut a straight taper between
the ends for the new sub floor to set on. Unfortunately, this was not the case.
After preparing a couple of them we tested for fit. The slab also has a significant
but unanticipated crown near the center that varies from one joist to the next.
After custom shaping the first ones with a hand plane, I finally figured out that
we could set a 2x4 on the slab, scribe it to fit the curve and cut it on the band
saw for a nearly perfect fit. Then we could mark both ends and cut a straight line
for the top and the sub flooring would fit perfectly. This was still a slow job but
much better than the first attempts. The sub flooring material is rated for joists
on 24 inch centers but I thought 16 inch spacing would give a more solid feel. At
32 feet, that is a lot of lumber to have to custom fit. There were some other
challenges along the way too, like keeping everything flat and level and being sure
we ended up at the right height for the patio door since we started at the other end.
Finally, I always thought the room was 32 feet long by 10 feet wide so four sets long
by 1-1/2 wide of 4x8 sub-flooring panels would be perfect. Actually, it turned out to
be 32 feet, 3 inches. This photo shows the result on the floor of hand planing just
one 2x4 joist. It was a tiring job and I do have a very good and sharp plane.
After shaping the 2x4 floor joists to fit the existing slab, we glued and screwed
them to the concrete. After completing each 8 foot section of joists, we then glued
and screwed the tongue-and-groove sub flooring panels onto them. The room is just
slightly under 10 feet wide so a sheet and a half fits with very little waste. The
left photo shows the first section finished. We started at the east end which will
be the master closet eventually rather than den but the floor needed to be continuous
from end-to-end. The other is the last section, showing the custom fitted joists,
ready for the sub flooring panels.
After finally finishing the sub-flooring, we took a break from the den and finished the piano alcove here. Judy was tired of the living room being an unusable jumble.
The next step in the den was the laundry closet at the far end. Since we purchased
this house, the laundry has been in the kitchen with the dryer venting into the
garage. This, of course, causes not only a significant amount of lint in the garage,
which doesn't look particularly good on a black car, but also raises the humidity in
the garage to a high level. With my woodworking tools moving to the garage, that was
not going to be acceptable. In Phase 6 we discussed the
plumbing that was contracted for the new laundry. Now it was time to build the closet
surrounding it. I built the walls and storage shelves and tiled the floor. Then my
son helped move the machines. It has now been tested and works perfectly. The closet
is a little tight for access to all the shelves but it is workable. Here it is first
roughed-in then finished and ready with the machines and shelves installed. There will
be louvered doors to close it in after the rest of the walls and floor are finished.
The stackable Bosch washer and dryer are fine machines for sure. That area on the right
with all the stacked moldings and the window air conditioner will eventually become
another glass block window with a wet bar below. We are still "under construction"
at this point.
Well, we got a break between other stuff and decided to install the glass block window
for the bar before winter comes. Here it is seen from inside the den as well as outside.
The last photo tries to show its relationship with the older three windows at the garage.
The next step is again not in the den but still had to be accomplished at the same time. The old laundry area in the kitchen had to be reconfigured for the secondary refrigerator that had been in the den since being displaced by the original kitchen remodel. That process is also described fully here.
Now, with those "aside projects" done maybe we can finally finish the den. Check back soon as we intend to finish as soon as practical.
Oh, wait! I almost forgot that there has to be a wall dividing the old 32 foot area and separating the "den" from the master bedroom walk-in closet. I have to do at least the major construction in the closet area before building that wall; otherwise, construction access will be much more difficult. Therefore, we will take yet another side-trip into the Master Bedroom & Walk-in closet phase.
Now with the closet, still not finished but at least usable, I can return to the den.
Moving the large lowboy into the closet made room to move the exercise bicycle from
the den to the bedroom. After moving more smaller tools to the garage, some other stuff
to the shed and some others to the dumpster, I almost have room to work in the den. I
started by sanding and finishing sheetrock joints that had not been done. I finished
around the windows with a typical sheetrock face cut very carefully to fit tight to
the window with metal outside corner where it meets the walls. This did not seem like
a practical solution for the door, however. The distance from the door to the wall was
just over an inch. Trying to cut that narrow a strip and then nail it to the frame so
close to the door just seemed unlikely to succeed. I opted to use wood instead. That
meant no metal corner was needed and I could use the brad nailer that close to the door
frame without danger of damage to it. But I then had to scribe it to match the wall.
These photos show the result with the blue painter's tape to protect the metal frame
from sheetrock compound and left in place for later primer. With primer now on the raw
sheetrock of the east and south walls, they are ready for the paneling. This will reduce
some of the clutter and make more working space in the room.
Finally Time for Inside Finishing
The rest of the den required several months. I just can't seem to work as many hours in a day as I could 15 years ago. By this time we had decided that bead-board paneling was the right thing for the walls. We searched all over town and all we found was rough, ugly stuff that looked like yellow pine. Finally, one day we were at Lowes, where I am certain we had searched before, getting something else when Judy noticed a small stack of what looked like bead-board. It turned out to be a really nice unfinished birch veneer, full 1/4 inch thick, 4x8 sheets with lap joints at either side. The product name was "Patriot Bead" from Patriot Timber Products, Inc. I had calculated that we needed 11 sheets but to be safe, I bought 12. They were closing this item out and there were only 15 sheets left so they gave me all of them. That turned out to be my good fortune as I used them all. I have several small cutoffs left that I might be able to use for some cabinetry in the closet and one full width sheet but short by a little over a foot. So much for my estimating.
My original idea was for a sort of white-washed look on the paneling but we finally decided on a natural finish with just a couple coats of clear polyurethane finish. It took a while to get the paneling installed as I pre-finished everything first. Due to working in the rather small room with father large panels, I was typically limited to three pieces at a time. That is "cut pieces", not necessarily full sheets. It takes a day to apply the natural stain and wait for it to dry then another day for two coats of poly and wait for it to dry then the third day I could fit and install the pieces. Fitting and installation was complicated slightly by the fact that the panels were still 4 feet wide but reduced by the 3/8 inch lap joint when installed, making a challenge in consistently aligning with the 4 foot stud spacing.
I started on the east wall which was fairly straight forward except for the ceiling
slope. The south wall was next and its only special considerations were the window and
patio door. these photos are of those two walls finished. I did have to fit in a small
piece over the door to avoid cutting another full sheet. This required hand making one
side of the lap joint. Then, after paneling both walls around the laundry, I decided to
not panel the wall behind the bar. I thought a break in the design with some appropriate
wallpaper or something else would look nice. That proved to be a wise decision since using
a sheet on that wall would have left me short by one or at least I would have to piece
something together to get it done. This last photo is of the laundry wall, also finished.
Yes, there is also clutter but, although we are getting closer, this is still a
"construction zone." The clutter is temporarily stored in the area the bar will
eventually occupy. It consists of tools still needed, doors and other minor bits and pieces
that may or may not be useful at some time.
Finally I got to the the north wall, the one with the kitchen passthrough. I started at the
west end of the wall and quickly realized I not only had to line up with studs and the opening
but also fit tightly around the extending counter top and corbel and provide for a "ship's
light." The photo gives an idea of complexity of the final piece. Then there are three
corbels supporting the counter top that land on panel joints and had to be fit closely. At
the other end of the passthrough is another piece much like a mirror image of the first one.
It had the additional problem of wanting to butt against the "chimney" for the
kitchen range vent. I wanted a tight fit so no moulding would be needed. This other photo
shows that fit. The other side of the chimney was similar fit-wise but the only other obstacle
on that end of the wall was another door.
With the paneling installed, it was time to pre-finish all the trim woodwork and moldings. I had to get that done before laying the flooring or it would have to be done outside or at least in the garage but certainly not over that new floor. These moldings included inside and outside corner for the paneling, crown, base, shoe, window stools and aprons and cap moulding for where the paneling doesn't reach the ceiling. Again, there was just too much of it to finish in one session and, like the paneling, it was at least two days for each session. The extending factor here was an almost constant rain storm for our wettest September on record. Many days were lost waiting for suitable humidity.
Then, with all trim pre-finished and stored, I started installing the crown moulding. The
ceiling slope is only 10-1/2 degrees so not as severe as a typical cathedral ceiling so
I hoped that I would be able to cope the corner joints. Well, as luck would have it, the
moulding is too complex and wide enough that I just couldn't make it fit acceptably. My
fit was all right for a flat ceiling but I was not satisfied with any fit I could make at
the required slope. Yes, I studied the tricks proposed on YouTube but did not like any of
them. I finally opted for inside corner blocks. They are not as obtrusive as I feared. These
photos show one at the high side of the ceiling and one at the low side. Notice that the
rosettte above the laundry had to be custom fit around the corner block. The corresponding
outside corner block, however, was an entirely different matter. It was so large it would
have overpowered the wall, maybe even the whole room. It was not acceptable so I spent
considerable time carefully fitting the outside miter at the outside corner of the laundry
closet. This was done by experimenting with the angles by trial-and-error. There are actually
four angles involved. It is not perfect as it, of course, cannot be perfect but close enough
and looks a whole lot better than the block would have. This last photo is the final result
and also shows the corner block above the bar window.
Since the paneling doesn't reach the ceiling on the north half of the room, I installed cap moulding and painted the walls above. To cover the raw edge of the plywood paneling around the window, passthrough and chimney I installed outside corner molding. The corner moldings for the paneling around the patio door and, of course, the base and shoe will have to wait until after the flooring is down. I did temporarily lay a piece of the flooring at both the doors into the living room and the laundry so I could install the door case but left the plinth blocks at the bottom off for now. Speaking of the door case, the door jamb width matches a 2x4 wall with half-inch sheetrock on both sides. My walls now have another quarter inch of paneling on one side. In order for the case the meet the jamb, I had to rip quarter inch strips to glue to one edge on the back side of every piece of case, plinth blocks and rosettes. This also meant leaving a one inch space at the corresponding edges of the paneling around the doors to accommodate that strip.
We decided to continue the paneling on the chimney to the ceiling. This photo shows the detail
of trimming it out, including fitting the corner moulding into the crown. The little framed
panel to the right is a cover for an electrical junction box that was necessary during the
early stage of wiring. It also gives a good view of the paneling cap moulding. Another minor
problem appeared under the passthrough counter top. There was an angled structural piece that
extended out beyond the wall. I covered it with paneling then closed the gap below with cove
moulding as shown here. I do have that little piece of Formica that appears to be missing at
the end of the counter top. And I still need to paint the underside of the counter top. Now,
it is finally time to clear out all the left over materials and tools and lay the flooring.
Having recently done the closet, I expected the flooring to be hard
on my old body and I was right. It took a total of 10 hours, spread out over 4 sessions, with
a lot of help from Judy. She pulled boards randomly from three cartons at a time and laid them
so I could stay on the floor installing them. That way I only had to get up to cut the last
one on each row then the first one for the next row. That did save a lot of getting up and down.
I forgot to use knee padding the first day and my knees will take much time to recover. Starting
at the north wall, the first half of the floor with the bar area at the far end, the flooring
runs were 20-1/2 feet and each plank was just under 4 feet. You can do the math or trust me, that
makes a challenge to avoid too short pieces and joints too close together. The south half was a
little easier, being 19-1/2 feet. The only complications were notching pieces at the laundry
door and getting the last 2 rows down where there is not enough distance from the wall to swing
the hammer. I trimmed 1/4 inch off the width of the last row, except at the patio door where I
decided it was worthwhile to again notch for a better finish at the door. And here it is before
installing the base but with plinth blocks. Now that requires another recovery day.
Okay, maybe a couple of recovery days. Installing the base was relatively uneventful except for
a strip under the chimney which is now only 1-1/4 inch above the flooring. You can't really see
it, even lying on the floor, but I thought it best to still seal the wall to the floor. Actually,
a little more work went into the base corner blocks and fitting the paneling corner moldings.
First, I decided to add outside corner blocks on both sides of the patio door. Of course, the
local sources had changed the style they stocked now with some fancy gizmo on the top since my
original purchase. I decided to just cut that off to look almost like the inside corners I had
and preferred. Then the cutout on the back to fit around the corner was not nearly deep enough
so I had to correct that. Finally, paneling corner moldings set on top of all the corner blocks
and one has to meet a crown corner block at the top. All that had to be shaped to look like it
really belonged there. The photos show the tight fit under the chimney and one of the inside
corner pieces fit to the crown corner.
The last piece of the floor puzzle was the transition strips at all the doors. The laundry door was simple enough as the new flooring was very close to the thickness of the tile in the laundry so a simple T-Molding worked. The door to the living room was not so simple. The level of the den flooring and the living room slate are not the same so a step-down transition strip was needed but that was too much difference. With some very careful handling of the molding on the table saw because of fingers too close to the blade, I was able to alter it to fit. The patio door also required a step-down molding but some sub-surface work had to be done first. Finally, Judy had bought a Levelor vertical blind at the Habitat for Humanity outlet store, that had never been completely unpacked, to use at the patio door. I soon discovered why it was donated. The slats could be opened from either end, which seemed useful, but when opened, they all hung in the middle of the door, which did not seem so useful. Fortunately, I was able to modify it so they all park at either end. Next she is starting on a roman shade for the window. I have now assembled the breakfast table in the room and we are enjoying using it.